Sandy Springs capital project: Abernathy Road Shared-Use Path built with Transform 285/400 (Abernathy Road Shared-Use Path built with Transform 285/400)

Phase: CST. Project type: Shared-Use Path. The reconstruction on Abernathy Road will include a 10 ft Shared-Use Path. The interesection will be modifed to be a DDI.

PARTIES AS STATED
GDOT

NEARBY ON THE RECORD · Fulton County

  1. ROADS JAN 01 2028 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 15)

    Project type: Bridge Replacement. Construction year stated: 2028.

  2. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 1)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  3. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 12)

    Project type: Bridge Replacement. Construction year stated: 2027.

  4. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 13)

    Project type: Bridge Replacement. Construction year stated: 2027.

  5. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 14)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  6. ROADS JUL 15 2026 · FULTON · GEORGIA DOT PROJECT HUB

    Road project M006940: Test Project Created to Validate TPRO v06.01.02

    Construction Work Program · Preliminary Engineering · Routes: 0000 · Cities: Atlanta, Not City, Port Wentworth · test 2/14 6:36 tEST 5/15