Road project 0013762: SR 60 FROM SR 400/LUMPKIN TO YELLOW CREEK ROAD/HALL
Construction Work Program · Widening · Cities: Not City · Funding: NEPA · GDOT project PI 0013762 consists of widening and improvements along State Route 60 in Hall and lumpkin counties Georgia. The project is approximately 4.87 miles starting at the SR 60/SR 400 intersection in Lumpkin County and continuing south to just north of Yellow Creek Road in Hall County. The existing road is a principal arterial (rural) with two lanes for most of the project length. Widening and improvements along the corridor are required due to congestion issues and high crash rates. There are two bridge culverts within the project limits, one at Long Branch and another at Yellow Creek. The existing right of way varies from 55-ft to 165-ft and required right of way is anticipated throughout the corridor. The design speed of the project will be 55 mph and decreases to 45 mph just north of Yellow Creek Road.