THE WIRE → FULTON → RECORD Nº 007153
ROADS · DEC 17 2024 · FULTON COUNTY
Road project 0015295: CS 2003/CENTRAL AVE @ CSX #279974G IN ATLANTA
Construction Work Program · Bridges · Cities: Atlanta · Funding: NEPA · This project consists of the reconstruction of the roadway approaches to the Central Avenue Viaduct between Martin Luther King Jr. Drive and Decatur Street, and the replacement of the Central Avenue Viaduct, except for the portion over the MARTA tracks, in the city of Atlanta. The typical section will consist of four one-way lanes, two 10’ wide lanes and two 11’ wide lanes, with 6” header curb urban shoulders. The project will also include 4” sidewalks for pedestrians on both sides of the roadway.