THE WIRE → FULTON → RECORD Nº 007178
ROADS · JAN 08 2020 · FULTON COUNTY
Road project 0015890: CS 654/10TH ST @ I-75/I-85; INC WILLIAMS ST & TECHWOOD DR
Under Construction · Miscellaneous Improvements · Cities: Atlanta · Funding: NEPA · The proposed project is centered on the 10th St Bridge over I-75/85. The width and number of the travel lanes along 10th Street are proposed to be reconfigured to 11' lanes with a 1' buffer to the barrier & 11' left turn lanes allowing for 9.5'sidewalks on both sides & a 10' separated 2 wy cycle track on the south side. The lanes on Williams St south of 10th St are to be narrowed to 11 ft & shifted to the west to construct a separated 2 way cycle track. The existing 42ft pavement width of Techwood Dr will be restriped to utilize the extra wide existing 22' wide northbound lane to create room for a 2 way cycle track from 10th St to the Turner Broadcasting entrance on the west side of Techwood Dr.