THE WIRE → FULTON → RECORD Nº 007317
ROADS · DEC 19 2024 · FULTON COUNTY
Road project 0018304: SR 3/US 19 @ CS 2368/GREENSFERRY AVE/MCDANIEL STREET
Construction Work Program · Intersection Improvement · Cities: Atlanta · Funding: NEPA · The proposed project would provide two northbound and two southbound travel lanes with a raised concrete median on Northside Drive at the intersection. The project also provides a left turn, through-right, and right turn lane on McDaniel Street WB and a left turn, and through-right on Greensferry Avenue EB. To accommodate high pedestrian volumes in the area, the sidewalk is proposed to be eight feet on Northside Drive and vary five to eight feet on Greensferry Avenue/McDaniel Street. The proposed project will be coordinated with PIs 0018303 & 0018343 to the south and PI 0018302 to the north to determine construction timing and temporary conditions until the final build out can be constructed. CR - 05/10/2024