Road project 0021239: SR 120 FROM BOLES ROAD TO RIVER MILL DRIVE

Construction Work Program · Widening · Cities: Duluth, Johns Creek, Not City · Funding: NEPA · This project was originally programmed to widen State Route (SR) 120/Abbotts Bridge Road from SR 141/Medlock Bridge Road to Peachtree Industrial Boulevard from two to four through lanes. The total project length is approximately 2.7 miles, which includes a 1500’ tie-in to SR 120 west of SR 141 and a 1000’ tie-in east of Peachtree Industrial Boulevard. Both SR 141 and Peachtree Industrial Boulevard would be improved and widened for approximately 1000’ in each direction approaching SR 120. Parsons Road would also be improved and widened to 1250’ south of SR 120, and Boles Road would be improved to 1000’ north of SR 120. All other side roads would be improved to a maximum of 500’ from SR 120. The existing SR 120 bridge would be widened and/or reconstructed across the Chattahoochee River. All signalized intersections would be modified

NEARBY ON THE RECORD · Fulton County

  1. ROADS JAN 01 2028 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 15)

    Project type: Bridge Replacement. Construction year stated: 2028.

  2. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 1)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  3. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 12)

    Project type: Bridge Replacement. Construction year stated: 2027.

  4. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 13)

    Project type: Bridge Replacement. Construction year stated: 2027.

  5. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 14)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  6. ROADS JUL 15 2026 · FULTON · GEORGIA DOT PROJECT HUB

    Road project M006940: Test Project Created to Validate TPRO v06.01.02

    Construction Work Program · Preliminary Engineering · Routes: 0000 · Cities: Atlanta, Not City, Port Wentworth · test 2/14 6:36 tEST 5/15