Road project 722010-: SR 400 FROM SR 140/HOLCOMB BRIDGE RD TO MCFARLAND RD GRTA

Under Construction · Widening · Routes: 040000 · Funding: NEPA · This project adds lanes and a median barrier to the existing median of SR 400 from Holcomb Bridge Road to McFarland Road. One lane will be added northbound from Holcomb Bridge Road to Haynes Bridge Road. Two lanes will be added northbound from Haynes Bridge Road to Windward Parkway. One lane will be added northbound from Windward Parkway to McFarland Road. One lane will be added southbound from McFarland Road to Haynes Bridge Road. In addition, five locations have been identified where noise walls will be constructed. This project is part of the Governor's Fast Forward Program.

NEARBY ON THE RECORD · Fulton County

  1. ROADS JAN 01 2028 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 15)

    Project type: Bridge Replacement. Construction year stated: 2028.

  2. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 1)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  3. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 12)

    Project type: Bridge Replacement. Construction year stated: 2027.

  4. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Bridge Replacement (map feature 13)

    Project type: Bridge Replacement. Construction year stated: 2027.

  5. ROADS JAN 01 2027 · FULTON · CITY OF JOHNS CREEK TRANSPORTATION PROJECTS

    Johns Creek transportation project: Intersection/Operational Improvement (map feature 14)

    Project type: Intersection/Operational Improvement. Construction year stated: 2027.

  6. ROADS JUL 15 2026 · FULTON · GEORGIA DOT PROJECT HUB

    Road project M006940: Test Project Created to Validate TPRO v06.01.02

    Construction Work Program · Preliminary Engineering · Routes: 0000 · Cities: Atlanta, Not City, Port Wentworth · test 2/14 6:36 tEST 5/15